Project components of this alternative are as follows (RDEIR p.V-4):
- 215 Residential Units (a 33% reduction)
- 125,000 s.f. Commercial/Retail (a 35% reduction)
- 100 room hotel (same as proposed action)
- 4,368 s.f. hotel restaurant (same as proposed action)
- 20,000 s.f. restaurant (1,092 s.f. less than proposed action)
- 4,175 s.f. science center (same as proposed action)
- 3,510 s.f. meeting space (same as proposed action)
- no theater (the proposed action included a 99-seat theater)
- 219,134 s.f. open space (same as proposed action, Note: this number is inflated as it includes "open space" that should not be counted under SEADIP)
- 82 feet maximum height* (a 68 ft. reduction from proposed action)
It should be noted that Planning Staff has not released the Planning Commission staff report. This information is expected to be available on Friday, October 7. The Second + PCH Project will be heard by the Planning Commission on Wednesday, October 12 in Council Chambers.