May 30, 2010

Seaport Marina Hotel and Second + PCH Project, Traffic Comparison

Using information found in the Second + PCH Draft EIR (Table 5-2: Project Generation Forecast, Appendix J), following is a table comparing the number of vehicle trips associated with the current Seaport Marina Hotel and the number of vehicle trips associated with the proposed Second + PCH development:


Time Period

Seaport Marina Hotel

Second + PCH Project

% Change

Weekday AM Peak

54

372

+ 689%

Weekday PM Peak

57

902

+ 1,582%

Saturday Peak

69

1,209

+ 1,752%


A comparison of the traffic associated with the previously proposed Lennar Project and the currently proposed iteration can be found here.